April 2026
14.04.2026
Construction of the first stage of construction -70%
Installation of the monolithic frame of the 1st stage of the section 1.1- 90%, the work of the rotational structures on the 8th floor is being carried out
Arrangementof the monolithic frame of the 1st stage of the parking lot - work is being carried out on the reinforcement of the floorboards
Masonry1 stage section 1.1 - 60%, work is being carried out on 5-6 floors