Construction progress

April 2026
Construction of the excavation of the 1st phase of construction — 70 percent completed.
Arrangement of a monolithic frame of the 1st stage of the parking lot - work is being carried out on the reinforcement of the floor slab.
Section 1:
Installation of monolithic frame section 1.1 — completed by 90%, work is being carried out on vertical structures on the 8th floor.
Masonry section 1.1 — 60% completed, works are carried out on 5-6 floors.
Installation of vertical waterproofing of section 1.1 — 80% completed.
Arrangement of filling the sinuses of the excavation section 1.1 — completed by 70%.
Section 2:
Arrangement of the pile field section 2.1 - work started on the installation of test piles

March 2026
Section 1.2-1.3
- Construction of the pit -80%
Section 1.1
- Installation of waterproofing -80%
- Construction of the frame of the building —90%
- Installation of masonry -20%
- Installation of ventilation units -20%
Section 2.1
- Construction of the pit -100%
Parking 3
Foundation installation -90%

February 2026
Section 1
Installation of vertical waterproofing of the plinth is completed
Arrangement of the floor slab of the 5th floor of section 1
Construction of the pit section 1.2, 1.3

Januar 2026
Installation of vertical waterproofing of the plinth
Arrangement of the floor slab of the 3rd floor of section 1
Completed work on the construction of the pit section 2
Arrangement of concrete preparation of section 1