Construction progress

Ми готуємо для вас пости, скоро тут буде не порожньо

April 2026

14.04.2026

Construction of the excavation of the 1st phase of construction — 70 percent completed.

Arrangement of a monolithic frame of the 1st stage of the parking lot - work is being carried out on the reinforcement of the floor slab.

Section 1:

Installation of monolithic frame section 1.1 — completed by 90%, work is being carried out on vertical structures on the 8th floor.

Masonry section 1.1 — 60% completed, works are carried out on 5-6 floors.

Installation of vertical waterproofing of section 1.1 — 80% completed.

Arrangement of filling the sinuses of the excavation section 1.1 — completed by 70%.

Section 2:

Arrangement of the pile field section 2.1 - work started on the installation of test piles

Детальніше

March 2026

13.03.2026

Section 1.2-1.3

  • Construction of the pit -80%

Section 1.1

  • Installation of waterproofing -80%
  • Construction of the frame of the building —90%
  • Installation of masonry -20%
  • Installation of ventilation units -20%

Section 2.1

  • Construction of the pit -100%

Parking 3

Foundation installation -90%

Детальніше

February 2026

13.02.2026

Section 1

Installation of vertical waterproofing of the plinth is completed

Arrangement of the floor slab of the 5th floor of section 1

Construction of the pit section 1.2, 1.3

Детальніше

Januar 2026

15.01.2026

Installation of vertical waterproofing of the plinth

Arrangement of the floor slab of the 3rd floor of section 1

Completed work on the construction of the pit section 2

Arrangement of concrete preparation of section 1

Детальніше

Contacts

Sales Department, Lviv

Staryi Rynok Square, 8
+38 (067) 837 00 22sales@intergal-bud.com.ua
Directions

Address of the object

Zoryana Street, 39
Plot a route

Free consultation

Дякуємо!
Ваша заявка отримана
Упс, нажаль щось пішло не так