August 2026
13.08.2026
Building 1, section 1
- Installation of aluminum structures completed
- Heating pipe installation and wall plastering are underway
- Roofing installation for the section is nearing completion
- Window installation is nearing completion
Building 1, sections 2-3
• Frame installation is underway
Building 1, sections 6-7
- Excavation and foundation slab installation completed
- Frame installation is underway
- Monolithic frame installation has begun
Parking
- Horizontal foundation waterproofing and vertical wall waterproofing for parking garage No. 2 have been completed