May 2026
14.05.2026
The construction of the pit of the 1st phase of construction has been completed
The installation of the monolithic frame of the 1st stage of the parking lot has been completed
Section 1
Installation of the monolithic frame of the 1st stage of section 1.1- work completed by 95%
Masonry of the 1st stage section 1.1 - 70%, work is carried out on 6-7 floors
Installation of a monolithic frame of section 1.2-1.3 - work has begun on the installation of vertical structures of the plinth